SDLC/SEPM MCQs based on UML, Extreme Programming, Agility, Development Models

Hello Everyone!


The MCQs are based on basics of Software Project Management. The topics included are UML Diagrams, SRS (Software Requirements Specification), Software Development Models, Agility, Scrum and Extreme Programming. These are the general topics in Software Development Life Cycle (SDLC), also known as Software Engineering and Project Management (SEPM).



Q 1) Which of the following is the way of ensuring that the tests are actually testing code?

a. Control structure testing
b. Complex path testing
c. Code coverage
d. Quality assurance of software

Solution: c) Code coverage


Q 2) Which of the following is not a software testing generic characteristics?

a. Different testing techniques are appropriate at different points in time
b. Testing is conducted by the developer of the software or an independent test group
c. Testing and debugging are different activities but debugging must be accommodated in any testing strategy
d. None of the mentioned

Solution: a) Different testing techniques are appropriate at different points in time


Q 3) Which of the following term is best defined by the statement: The underlying technology on which the system is built is superseded by new technology?

a. Technology change
b. Project competition
c. Requirements change
d. None of the above

Solution: a) Technology change


Q 4) Software mistakes during coding are known as ____.

a. Errors
b. Failures
c. Bugs
d. Defects

Solution: c) Bugs


Q 5) Effective testing will reduce ____ cost.

a. Maintenance
b. Design
c. Coding
d. Documentation

Solution: a) Maintenance


Q 6) Testing should be conducted for every possible ____.

a. Data
b. Case
c. Variable
d. All of the above

Solution: d) All of the above


Q 7) Which of the following risks are derived from the organization environment where the software is being developed?

a. People risks
b. Technology risks
c. Estimation risks
d. Organizational risks

Solution: d) Organizational risks


Q 8) Cyclomatic Complexity method comes under which testing method?

a. Yellow box
b. White box
c. Gray box
d. Black box

Solution: b) White box


Q 9) Is a customer involved in test development and validation in XP (Extreme Programming)?

a. Yes
b. No
c. It may vary from customer to customer
d. None of the above

Solution: c) It may vary from customer to customer


Q 10) User requirements are expressed as _____ in XP (Extreme Programming)?

a. Implementation tasks
b. Functionalities
c. Scenarios
d. None of the above

Solution: c) Scenarios


Q 11) Risk management is now recognized as one of the most important project management tasks.

a. True
b. False

Solution: a) True


Q 12) Which of the following risks are derived from the software or hardware technologies that are used to develop the system?

a. Managerial risks
b. Technology risks
c. Estimation risks
d. Organizational risks

Solution: b) Technology risks


Q 13) Incremental development in XP (Extreme Programming) is supported through a system release once every month?

a. True
b. False

Solution: b) False


Q 14) Which is a black box testing technique appropriate to all levels of testing?

a. Acceptance testing
b. Regression testing
c. Equivalence partitioning
d. Quality assurance

Solution: c) Equivalence partitioning


Q 15) Test cases should uncover errors like ____.

a. Non existent loop termination
b. Comparison of different data types
c. Incorrect logical operators or precedence
d. All of the above

Solution: a) Non existent loop termination




PAGE 1  |  PAGE 2  |  PAGE 3  |  PAGE 4

Comments

Popular posts from this blog

50 + Interview Questions/Experiences of TCS DCA April 2021

Hello Everyone! This post is dedicated to the Interview Questions asked in TCS DCA. DCA which is Digital Capability Assessment is usually conducted for the internal employees of TCS who are selected for the Ninja profile. If DCA is cleared successfully, then the candidates are offered Digital profile. That means the profile changes from Assistant System Engineer to System Engineer . This year i.e., in 2021, TCS conducted DCA for the candidates who have received offer letter but not joined TCS as an employee yet. The original DCA which is conducted for internal employees has a different pattern and is not discussed in this post. Rather this post is dedicated to the DCA conducted in March and April 2021 for 2021 recruits. The DCA was conducted on 19 th and 20 th March 2021. The test had two coding questions. To sucessfully clear DCA, all the test cases of both the codes must be passed. In March DCA, a lot of students faced compile...

UML - Object Diagram for Hospital Management System

Hello Everyone! Here is an example of an Object Diagram for Hospital Management System. Problem Statement - The hospital wishes to maintain a database to assist with the administration of its wards and operating theatre and to maintain information related to its patients, surgeons and nurse. Most patients are assigned to a ward on admittance and each ward may contain many patients. However, consultants (senior surgeons) in the hospital may have private patients who are assigned to private room. A nurse may or may not be assigned to a ward and she cannot be assigned to more than one ward. A ward may have many nurses assigned to it. Each ward is dedicated to a particular type of patient. A nurse may or may not be assigned to a theatre and she cannot be assigned more than one theatre. Theatre may have many nurses assigned to it. A patient may have number of operations. The information to be recorded about the operation includes the type of operation, the patients, the surgeons involv...

UML - Activity Diagram for Vending Machine

Hello Everyone! Here is an example of an Activity Diagram of a Vending Machine. Problem Statement - A vending machine accepts coins for a variety of products. The user selects the drink from products available through selection panel. If the drink is available the price of the product will be displayed. The user then deposits the coins depending on the price of the product. Coin collector collects coin after stipulated time. The controller will compare the deposited coins with the price. If amount is less than the price then an error message will be displayed and all deposited coins will be dispensed by the dispenser. Otherwise the drink will be displayed by the drink dispenser. Check out other UML (Unified Modeling Language) Diagrams - Use Case Diagram   Class Diagram   Object Diagram   Sequence Diagram Collaboration Diagram   State Diagram   Component Diagram   Deployment Diagram