Skip to main content

Project Management Question Paper Solution (MCQs) for 2021 Mumbai University Examination Semester 8

Hello Everyone!
This article is based on the Multiple Choice Questions asked in the University Exam for the subject Project Management - Institute Level Elective.

These MCQs were asked in the 2021 Mumbai University-BE-Semester 8 Exam for the subject- Project Management. Project Management is an Institute Level Elective and is common to all the branches. The question paper for each cluster is different. These MCQs were asked in the examination of one cluster. The question paper had 20 MCQs of 2 marks each.






Q 1) Which of the following is the most important element of Project Management Plan that is useful in Planning process?
a. Risk Management activities
b. Quality Assurance activities
c. Budget Control activities
d. Activity Resource requirements

Solution: d) Activity Resource requirements

Q 2) CPM is an acronym for ________.
a. Control Path Method
b. Critical Path Method
c. Cohesion Path Method
d. Control Path Model

Solution: b) Critical Path Method

Q 3) A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000?
a. Cost Variance
b. Management Overhead
c. Management Contingency Reserve
d. Schedule Variance

Solution: c) Management Contingency Reserve

Q 4) Activity Definition is typically performed by which of the following __________.
a. Project Manager who created the WBS
b. Project Team Members responsible for the work package
c. Project Officer
d. Project Stakeholder

Solution: b) Project Team Members responsible for the work package

Q 5) Expected risks in a project is represented in a tabular form by ________.
a. Risk Table
b. Assessment Table
c. Time Table
d. Round Table

Solution: b) Assessment Table

Q 6) A project has a 60% chance of a $100,000 profit and a 40 percent of a $100,000 loss. The Expected Monetary Value for the project is __________.
a. $100,000 profit
b. $60,000 loss
c. $20,000 profit
d. $40,000 loss

Solution: c) $ 20,000 profit

Q 7) The time taken to break even or pay back the initial investment is called as _______.
a. Back period
b. Payback period.
c. Cash back period.
d. Rate of Return.

Solution: b) Payback period.

Q 8) The expenditure and income taken place in a project is indicated by _______.
a. Cash flow forecast
b. Cost analysis
c. Fund flow
d. Technical forecast

Solution: a) Cash flow forecast

Q 9) The method which is carried out to calculate the earliest dates on which each activity may be started and completed is _________.
a. Backward pass
b. Forward pass
c. No pass.
d. Increasing pass.

Solution: b) Forward pass

Q 10) The shortest time in which we could expect to complete the activity, barring outright miracles is called as ______.
a. Optimistic Time
b. Pessimistic Time
c. Most Likely Time
d. Shortest Time

Solution: a) Optimistic Time

Q 11) Which of these is not one of the constraints of a project?
a. Scope
b. Team
c. Resources
d. Budget

Solution: b) Team

Q 12) Which is not one of the stages of Project Management Lifecycle?
a. Definition and Conceptualization
b. Management and Measurement
c. Planning and Budgeting
d. Execution and Control

Solution: b) Management and Measurement

Q 13) Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times for the three activities are 12, 15, and 10, then the earliest start time for Y will be _______.
a. 10
b. 15
c. 12
d. 100

Solution: ) 15

Q 14) The critical path is referred to as the _________.
a. Most direct path from the beginning node to the ending node
b. Shortest path in terms of time
c. Longest path in terms of time
d. Path with the largest amount of slack time

Solution: c) Longest path in terms of time

Q 15) A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of _______.
a. Finish-to-Start
b. Start-to-Finish
c. Start-to-Start
d. Finish-to-Finish

Solution: a) Finish-to-Start

Q 16) Resource requirement in project becomes constant while the project is in its what progress stage _________.
a. 40 to 55%
b. 55 to 70%
c. 70 to 80%
d. 80 to 95%

Solution: d) 80 to 95%

Q 17) What limits the options of the project team?
a. Constraints
b. Assumptions
c. Technology
d. Deliverables

Solution: a) Constraints

Q 18) The difference between the cumulative earned value ofthe work performed and the cumulative actual cost is known as ______.
a. Cost performance index
b. Cost variance
c. Budgeted costs
d. Cost quality index

Solution: b) Cost variance

Q 19) Which of the following does NOT generate changes to the Project documents?
a. Define Activities
b. Sequence Activities
c. Estimate Activity Resources
d. Estimate Activity Durations

Solution: a) Define Activities

Q 20) If the Earned Value is equal to Actual Cost, it means _______.
a. Project is on budget and on schedule
b. Schedule variance index is 1
c. There is no schedule variance
d. There is no cost variance

Solution: c) There is no schedule variance

Comments

Popular posts from this blog

Connecting GitHub with Jenkins - Step by step Tutorial

Hello Everyone, In this tutorial, we will learn how to create a New Item (Project), connect Git and GitHub to Jenkins and run the files from the Git repository on Jenkins. Jenkins is an open-source automation tool written in Java with plugins built for Continuous Integration purposes. Jenkins is used to build and test your software projects continuously making it easier for developers to integrate changes to the project, and making it easier for users to obtain a fresh build. Facing trouble with the installation of Jenkins? Click here to know more. NOTE: It is mandatory to install plugins for Git and GitHub before connecting your GitHub repository to Jenkins. If you're using Jenkins for the first time, you need to install the plugins. To know more about these plugins, check out Git and GitHub Plugins for Jenkins . This tutorial demonstrates executing python code which requires separate plugins. Know more about Python Plugi...

Statistics - MCQs

STATISTICS  This article contains few statistics MCQs related to mean, median, mode and standard deviation, asked in TCS Freshers placements. Q 1) The mean of the median, the mode and the range of the following data: 15, 10, 17, 13, 25, 17, 11, 18, 14, 19, 12, 20 a. 15 b. 16(2/3) c. 16 d. 15(1/3) Solution: c) 16 Arrange the data in increasing order- 10,11,12,13,14,15,17,17,18,19,20,25 Median = (Sum of the middle two terms)/2 = (15+17) /2 = 16 Mode = Number repeating the most number of times = 17 Range =10 to 25 = 15 Mean of median, mode and range = (16+17+15) /3 =16 Q 2) What is the mean of the mode and the median on the following data? 12, 28, 26, 27, 17, 16, 22, 25, 15, 16,...

IoE (Internet of Everything) Question Paper Solution (MCQs) for 2020 Mumbai University Examination Information Technology Semester 8

Hello Everyone! This article is based on the Multiple Choice Questions asked in the University Exam for the subject Internet of Everything. These MCQs were asked in the 2020 Mumbai University-BE-Information Technology-Semester 8 Exam for the subject- Internet of Everything. The question paper for each cluster is different. These MCQs were asked in the examination of one cluster. The question paper had 25 MCQs of 2 marks each. Q 1) ________ involves making smaller and smaller things with the ability to connect and interact. a. Smart Tech b. Micro Tech c. RFID Tech d. Nano Tech Solution: d) Nano Tech Q 2) RFID stands for? a. Radio frequency identification b. Random frequency identification c. Random frequen...